Palma City Council grants permits for the total remodeling of Son Moix: in 2024 the athletics track will be history

Give 1 Sec To Rate This Article post

ANDhe Palma City Council has officially granted authorization for the total remodeling of the Mallorca stadium. The ‘new Son Moix’ project will start with the first phase of the works as soon as the last LaLiga match is played, scheduled for May 16.

The club will allocate 20 million euros to the project, thanks to the money obtained from the ‘LaLiga Impulse’ with CVC. The first phase consists of bringing the Tribuna Sol closer to just 8.5 meters from the pitch in works that will begin after the final whistle of the last match played in Son Moix. This first reform is expected to be completed before the start of the 2022/2023 season.

Execution deadlines and project phases

The planned phases of the works that will begin in May and are to be completed by mid-2024 are as follows:

Phase I: Construction of the stands of the lower lateral ring in the current Sol stand and of the roof on the same stand.

Phase II: Construction of the North end and the stands of the lower ring of the North end (Camí dels Reis)

Phase III: Construction of the stands of the lower ring of the current Grandstand.

Phase IV: Construction of the stands of the lower ring of the South end.

Cort has agreed with Mallorca to extend the use of Son Moix until 2064

In addition to authorizing the start of the first phase of remodeling the stadium, the Palma City Council has announced the renewal of the agreement for the use of the facilities with Real Mallorca for a further 25 years, so the use of Son Moix, now under the name of ‘Visit Mallorca Estadi’, runs until 2064.